OBU Home
Apply Online | Give Online
North Dallas Center
North Campus Redevelopment

Residential Village

The new residential village is the heart of this redevelopment project. When it is complete, over 500 beds will have been replaced with beautifully designed, state-of-the-art facilities surrounding "The Circle".

August 20: Dedication was held today and the project was completed just in time. Well, other than asphalt in one parking lot and some landscaping. The women's hall and five houses were named for the Gosser family. Other houses were named for Mom Chu, John and Yvonne Cloud, Andy and Jeanna Westmoreland and the Daniel family. It was a great day for Ouachita.

August 10: Almost there! Completion date and move-in date are both approaching quickly. The women's hall is finished other than hanging blinds on the windows and a final cleaning. The men's hall is a few days behind but will be complete by August 17. Dedication of the student village is scheduled August 20.

 

 

Theater Room                                                     Bathroom

 

July 10: Finishing up painting and floor staining in Building 1 and installing technology. Building 2 still has a long way to go but it will be ready!

 

June 29: Building 1 is complete other than some ceiling work and staining the floors. The connector between buildings is almost complete.

June 19: Here's a photo of one of the four terraces (sundecks) on the buildings.

June 12: Below is a photo of Daniel before the demolition began. Some work had already been done at this point to remove any materials containing aesbestos and to remove any equipment that can be re-used. You can follow the demolition live at http://www.obu.edu/northcampus/ncstream.asp. You can also see some of the sitework in the Circle from this camera.

 

June 9: The building exteriors are now complete with the exception of some minor trim work. Inside, several suite are finished other then staining the floors and a second coat of paint. Work begain last week on the connector between the buildings. The connector will be a "gateway" between the Village and Sturgis. Daniel Hall has been prepared for demolition, which is scheduled to begin June 15.

 

Beginning connector                                              Bathroom vanity

April 28: It's official - dispite numerous weather delays, the two buildings in Phase 1 will open in time for fall move in! Originally, phase 1 was scheduled to be completed December 1 but our contractors are significantly ahead of schedule. We even have paint on the walls in some of the houses. This week, students are getting their housing assignments and will find out who gets to be in the first group of Student Village residents.

Bedroom - painted, light fixture hung                         Windows in connector between houses

Sundeck on building 2

March 24: Progress continues! Many of the same trades have continued working over the last month - electrical, plumbing, drywall, masonry, windows, etc. - but the way work progresses, progress is still obvious. With 12 houses  to complete, one house can appear to be much farther along as the workers progress from one end of the structures to the other. Weather is still a bit of an issue but the buildings should be in the dry very soon.

Windows in a connector between houses

February 20: The pace of the project seems to be picking up but that may simply be perception since there are so many obvious changes over the last few weeks. Two of the houses are complete on the exterior. Several of the suites have now been sheetrocked. The project is starting to look like home - I'm ready to move in!

Living Room                                                                           Bedroom

January 21: The housing project continues to progress well. Walking around the project, the various stages of completion are evident - from windows, drywall and roofing on one end to completing the exterior framing and preparing roof trusses on the other end.

Building 1 - Houses 1 through 4

Shingles on House 1                                           Windows

Drywall on ceiling, 4th floor                                   Beginning stone on exterior

December 22: Each time a new stage begins on the buildings, my thought is "the project is really starting to take shape now". That was certainly the case when the first roof structures were set into place. Standing at the north end of what will eventually be "The Circle" and looking into the center of the village, it is evident how impressive these new homes for Ouachita students will be.

Site                                                                       Building 2

House 1 and 2                                                      4th Floor

 Building 1 Corridor                                               Pouring 4th floor

November 21: The exterior framing of the buildings is approximately 90% complete. The interior wall framing continues - as a house goes up, work begins inside with framing walls and the "inside the wall" work (wiring, piping, ducts, etc). The exterior sheathing began this week as well.

Building 1                                                                     Building 2

House 1 & 2                                                            Building 1 south stairs

October 22: Framing started on the southmost end of the project - houses 1 and 12 - and will continue around to the northmost end of the circle, nearest Sturgis. As the contractors work there way around the framing is in various stages. In some areas, the houses are framed all the way up, in some only the first level is framed. Some floors have the decking installed, others have the second and third level slabs poured and the ductwork is beginning to be installed. Also, the mechanical contractor is installing much of the mechanical equipment in the central plant and construction of that "building" has begun.

 

September 23: The first steel beam was set in place today! Now this project is beginning to look like a building!

First Beam

Steel delivery                                                            Crane

September 19: After several rainy days, the slab for building 1 has been poured. The footings and underground utilities for building 2 will be compete by Monday and that slab will be poured beginning early Tuesday morning. Steel delivery will start on Monday as well and is scheduled to begin going up next Wednesday.

Pouring the Building 1 slab

Bldg 1 elevator pit being waterproofed                       Shows how close construction is to existing dorms

 

August 29: More rain! This has been an unusually wet August. Most of the past two weeks has been spent completing the water and sewer lines, working on storm drains and setting the footings for the buildings. The building slabs should be poured by September 8.

This is what rain does...                                          Installing rebar for the footings

Pouring building footings                                           Elevator pit

  

August 15: Rain! It was certain to happen eventually. It seemed as if we were going to get the building out of the ground without any weather issues but a major front came through, dropping about 8" of rain over 3 days. That much rain obviously leaves a mess and has slowed work for several days. Pouring building foundations was pushed back one week as a result. This week, the primary water line from the city was connected to a new line around the housing site. Work to relocate electric service to the area has also been completed.

Quite a pond, but no fish.                                       New 10" water line

August 1: The underground utility work is almost complete. The contractor is working quickly to get this phase of the project finished before students return for the fall semester. Also, this week installation of "geopiers" began for the foundation of the buildings. Interested in what a geopier is? In laymans terms it means digging a hole, pouring rock back in the hole (about one foot at a time) and ramming it over and over to create an extremely hard and stable surface for the foundation.

 

July 25: Most of the work this week has been to install underground utilities around the site and connecting to the central plant behind Tiger Den.

July 22: The footprint for Building 1 has been staked out. The foundation piers are scheduled next week. Also, the west parking lot site has been cut.

Building 1 Footprint staked out                            Daniel lobby

July 18: Work began in earnest this week. The Sturgis parking lot and Daniel lawn have disappeared as the site is prepared for construction. The loss of Daniel lawn is a sad thought but The Circle will more than replace that recreational space. Part of Daniel lobby was also removed this week because it was in the footprint of Building 2. The lobby is still there and usable - just a bit smaller.

We've suspected for the last several weeks that our original plan to open the first two buildings in August was too ambitious. That thought was confirmed this week as we set a projected completion date of December 1, 2009 for those buildings. Although the date change is a minor setback, it will ensure that the project is complete prior to move in and the additional time will improve the quality of construction.

Housing site                                                            Utility work behind Daniel

July 11: Over the summer, a number of important tasks have been completed related to the housing construction but much of it is hardly noticeable. Electric power lines and fiber optic cable have been moved, which allows us to keep power and network services running in the existing North Campus buildings as well as provide utilities for the future housing. The old tennis courts have been removed to make way for the central plant that will provide heat, air, hot water and other essentials to the buildings. Tiger Den though, was saved! Our plan had been to demolish the Tiger Den building but our architects found a way to keep that structure. It will be available for use this fall and into the future.